Questionaire



No.
QUESTIONAIRE
DESCRIPTION
1.
Origin Location
Binuang, Kintap, Asam – Asam, Sungai Danau, and Batu Licin ( South – Kalimantan of Indonesia)
2.
Product Capasity Metric Ton / Month
50.000 MT / Month +/- 10 %
3.
Quantity of Mining Location (Reserve)
50.000  -  300.000 MT/ Month +/- 10 %
4.
Element Percentage
-
5.
Surveyor
Sucofindo, Carsurin, SGS, Geoservice, CCIC, ect
6.
Gross Calorific Value ( SGS, Suco, Cars….etc )
5300 Kcal/Kg, 5500 Kcal Kg, 5800 Kcal/Kg, 6100 Kcal / Kg, 6300 Kcal/Kg, 6500 Kcal/Kg.
7.
Rejection Level
5000Kcal/Kg, 5300Kcal/Kg, 5600Kcal/Kg, 5800Kcal/Kg, 6100 Kcal/Kg, 6300 Kcal/Kg.
8.
Size
0 – 50 mm ( 80 % ) + 50 mm ( 20 % )
9.
Loading Port
Any Port of South Kalimantan - Indonesia
10.
Loading Point
Tabonio, Muara Satui, Muara Kintap, Tanjung Pemancingan, Tanjung Petang
(South Kalimantan of Indonesia )
11.
Loading Rate Metric Ton / Day
5500 MT up to 8000 MT / day
12.
Co-ordinate Latitude 
/ Longitude
Taboneo :
Latitude  03- 52 00 S,
Longitude 114 – 25 00 E, L.A.S : 20 M


Muara Kintap :
Latitude 03 – 05 00 S,
Longitude 115 – 27 30 E, L.A.S : 18M
Muara Satui :
Latitude  03 - 52.00
Longitude  115.31.30 BT.
Tanjung Pemancingan :
Latitude  03 – 12 20 S,
Longitude 116 – 22 09 E, K.W.S : 30M
13.
Water Depth
-
14.
Mother Vessel Size
Option
15.
Price on FOB Barge (Pontoon) / FOB Mother Vessel
Negotation
16.
Price Adjusting ( Period ie: every 3 Month)
Every 3 Months
17.
Payment Term ( L/C, Transferable )
L/C At Sight 100 %  Non Transferable, Confirm LC, Revolving
18.
Performance Bond (PB)
Performance Bond 2 %
19.
Site Visit
After Signing Contract and Received Draft L/C or SKBDN

Welcome To : PT. AQUARIUS MINERAL UTAMA